The notice that was late
A missed 28-day notice can cost a claim that was otherwise sound.
BuildCore tracks the letters that start contractual clocks, the hindrances behind an extension of time, the FIDIC claims against their Clause 20 deadlines, and the certificates and variations that turn entitlement into money.
A missed 28-day notice can cost a claim that was otherwise sound.
When the EOT application goes in, the record has to be assembled from diaries and email.
Retention, advance recovery and previous certificates recalculated by hand every month.
The Engineer's instruction is logged with its time bar.
The notice goes out before the deadline, on letterhead.
Particulars submitted against their own clock.
A variation order records cost and schedule impact.
The IPC deducts retention and advance recovery.
Certified, received and outstanding on the dashboard.
No. It tracks deadlines, records the facts and drafts letters on request. Your team decides, and the Engineer determines under the contract.
FIDIC 1999 and 2017, NEC4, and India's CPWD GCC 2023, NHAI EPC and HAM, and Indian Railways GCC 2022 — with a custom regime for everything else.
Yes. Each client IPC deducts retention and mobilisation-advance recovery at the contract's rates.
Modules on this page: Communications · Hindrance & EOT · Contract Management · Commercial & Finance
Tell us about your projects and we'll show you the parts of BuildCore that matter to you.