Product · Contract Management

Construction contract management, from award to the last certificate

Set up the client contract once — value, currency, retention, advance, bond, liquidated-damages rate and FIDIC edition — and BuildCore values each interim payment certificate from cumulative work done, deducts retention and advance recovery for you, and tracks every variation and FIDIC claim against its own clock.

BuildCore's client contracts dashboard: 7 active contracts, contract value, amounts certified and received, the outstanding balance and 6 open variation orders, all in rupees; contracts by status; a list of contracts with client, certified and received amounts; and recent variation orders with their status, schedule impact and cost.
Contract value, certified, received and outstanding — with the variation orders in flight. Sample data.
Why it matters

Contracts are won in the tender and lost in the administration

The money is usually in the contract. Getting it out depends on certificates, notices and securities handled on time.

Certificates built in spreadsheets

Retention, advance recovery and previous certificates recalculated by hand each month — and a single error carries forward.

Claims that miss Clause 20

A 28-day notice missed is an entitlement lost, however strong the claim.

Guarantees that expire unnoticed

Bank guarantees and advances need watching; an expired guarantee is a commercial risk the day it lapses.

Capabilities

What Contract Management does

Contracts and milestones

  • Client contracts with value, currency, retention percentage and cap, mobilisation advance and recovery, performance bond, LD rate and cap, payment terms and FIDIC edition
  • Live totals on every contract: certified, received and retention held
  • Payment milestones with percentage and amount, from pending to achieved, certified, invoiced and paid
  • A joint-venture register with partners and shares

Interim payment certificates

  • This period's gross worked out from cumulative work done less the previous certificate
  • Retention and mobilisation-advance recovery deducted automatically; LDs, other deductions and tax entered
  • A certificate is blocked if cumulative work goes down or exceeds the contract value
  • From draft to submitted, certified, invoiced and paid

Variations, EOTs and FIDIC claims

  • Variation orders — client, vendor or internal — with cost and schedule impact, linked to the change request, RFI, NCR or site instruction behind them
  • Variations tagged to the WBS, with a summary by WBS
  • FIDIC claims set up per project: 28-day notice and 42-day detailed claim for 1999, 28 and 84 days for 2017
  • Deadlines computed; a late notice flags the claim as time-barred and late particulars as late; the Engineer's determination records days and amount awarded
  • A claim raised straight from a variation order, and EOT requests with days requested and approved

Securities and deductions

  • Bank guarantees and letters of credit with days to expiry and a count of those expiring within 30 days
  • Advance payments with a recovery ledger that marks them fully recovered on its own
  • Liquidated damages: days late times the daily rate, capped (10% by default)
  • Back-charges against subcontractors, applied to their bills
How it works

A FIDIC claim, from event to determination

1

Event

The event and its date are recorded against the contract.

2

Notice

The notice deadline is computed — 28 days under both editions.

3

Particulars

The detailed claim goes in against its own deadline.

4

Flags

A late notice is flagged time-barred; late particulars, late.

5

Determination

The Engineer's award — days and amount — is recorded.

6

Outcome

Agreed, disputed or closed, with the full history.

Outputs

What comes out of it

  • Contracts, certificates, milestones, variations, EOTs and back-charges printed on your letterhead with signature blocks
Questions

Contract Management — common questions

The 1999 and 2017 conditions: each project records its edition, and BuildCore computes notice and detailed-claim deadlines from it — 28 and 42 days for 1999, 28 and 84 for 2017.

The claim is flagged time-barred the moment the notice deadline passes without a notice, so a lapsed claim is visible at once rather than at the final account.

Yes. Each interim payment certificate deducts retention and mobilisation-advance recovery at the contract's rates; LDs and other deductions are entered.

Yes — guarantees and letters of credit with their expiry dates, a count of those expiring within 30 days, and their release, claim or expiry.

See it on your project

See Contract Management on your own project

Tell us about your project and we'll shape the demo around Contract Management and the modules it connects to.